EXPERIENCE: (Total 10 years)
a. Summary Site Requirement
- Excellent Knowledge For Reading Drawing and detailing
- Very Good knowledge About pre-installation arrangement
- Very Good knowledge about Construction Planning
- Excellent knowledge about Initiated Inspection
- Good knowledge about Quality Control Conditions
- Excellent knowledge about Quantity Surveyor
- Excellent knowledge about Initiated Daily and Monthly Report
- Excellent knowledge about Initiated Shop Drawing for Construction
- Excellent knowledge about Initiated Material and Drawing Submittal
- Excellent knowledge about Prepare Bending List, Construction Method-Formwork,
Temporary work,..etc-.
b. Major Work
1.Contractor's Technical Office Manager (Main)
2.Contractor’s Construction Manager
Project : Prince Sultan Cultural Center (Total Cost 200,000,000 SR)
Location (Earth Google):
24 Deg 42' 59.71" North
46 Deg 37'19.38" East
Client :King Saud University
Consultant :General Military work
Contractor :Al mansouryah establishment
Duty :
-Responsible for detailing the project to engineers.
-Ensure that the construction work done according to Specification and Drawing.
-Discuss with project manager the priority for pouring and construct.
-Discuss with the project manager purchasing requests and its priority.
-Responsible for checking design for all element (Beams,Slab,Column) structurally according to ACI.
-Responsible for shop drawing for concrete dim,bar bending,surveyor, carpenter…..
1.Contractor's Technical Office Manager (Main)
2.Contractor’s Construction Manager
3.Do project manger duty from mar 2008 up to aug 2008
Project : Central Service Building for King Khaled Hospital (Total cost 97,000,000 SR)
Location (Earth Google):
24 Deg 42' 40.96" North
46 Deg 37'22.10" East
Client :King Saud University
Consultant :Khatib and Alami
Contractor :Al mansouryah establishment
Duty : (finished nearly 8000 cu.m concrete, 5 floor and 2 basement)
-Share project manager coordination between each discipline (Archtictural-HVAC-Plumbing-Electrical) with project manager.
-Share responsability with project manager for coordinate and monthly update the project schedule.
-Responsible for check inspection requests before submit to consultant.
-Detailing the projects for engineer for construction.
-Responsible for review and check scafolding design -saudi scafolding (SSF)-and submit it to consultant for approval.
-Responsible for start up the project (material, equipment,shop drawing..).
-Responsible for Mobilization (site fence, offices, electrical work, plumbing…).
-Responsible for shop drawing for surveyor, mason, concrete shuttering,steel rft bending list…..
-Share project manager prepare material purchase including but not limited steel ,shuttering ,scafolding, pipes, saw machine, polyethylene, tie rod, waterstop, cement, sand….
-Responsible for Proposal, installation pipe 500mm storm pipe to transfer exist storm tunnel in scope of building.
-
Period from Aug 2007 Up To Dec 2007
Contractor’s Construction Engineer
Project : Prince Sultan Cultural Center
Client : King Saud University
Consultant : General Military work
Contractor : Al mansouryah establishment
Duty :
-Share prepare project schedule and check it with consultant.
-Responsible for making bending list for foundation steel approximately 450ton.
-Responsible for Initiated inspection request.
Employer’s Site Engineer for Egyptian Electric Ministry (Sina zone)
Project :Ras Sedr/Sharm El Shikh High voltage Power Line
Contractor :Kahromica
Duty :
-Responsible for monitor progress
-Responsible for contractor’s invoices
- Ensure that the civil contractor constructs the civil and building works in line with
the design and applicable specifications.
SubContractor’s Technical Office Engineer
Project :Kohafa Waste Water Treatment Plant
Contractor :ABB SUSA
SubContractor :Engineering Construction Company (HINALCO)
Duty :
- Responsible for review calculation sheets for subcontractors.
-Prepare Steel Binding List and Follow up in workshop.
Contractor’s Technical Office Engineer
Project :Kohafa Waste Water Treatment Plant
Contractor :ABB SUSA
Duty : Responsible for review calculation sheets for subcontractors.
Employer’s Site Engineer for Egyptian Electric Ministry (Sina zone)
Project :Elarish High voltage S/S
Duty :-Responsible for construct the project.
Employer’s Site Engineer for Egyptian Electric Ministry (Sina zone)
Project :Sharm El Shikh High Voltage S/S
Duty :- supervisor for construction.
-Responsible for review calculation sheet and invoices.
Sub-Contractor’s Technical Office Engineer
Project : Tow Terminal Station for passing cable under SUIS Canal
Main Contractor :Schnider Electric Co.
Sub contractor : Engineering Construction Company (HINALCO)
Duty :-Responsible for quantity survey
-Responsible for prepare binding list
-Responsible for making purchase request
Sub-Contractor’s Technical Office Engineer
Project :New Mansora Water Treatment Plant(consist of 8 building
oxidation,filteration,….) 105,000 cubic meter water treatment per day
Main Contractor :ABB SUSA
Subcontractor :Engineering Construction Company (HINALCO)
Duty :-Prepare Calculation Sheet for invoices and review it with consultant.
Sub-Contractor’s Technical Office Engineer
Project : Fayoum Gas Development Project
Main Contractor : Egyptian Maintenance Co.
Sub contractor : Engineering Construction Company (HINALCO)
Duty :-Responsible for quantity survey.
Sub-Contractor’s Technical Office Engineer
Project :Wadi hof High Voltage S/S
main contractor :ABB high voltage
Sub contractor :Engineering Construction Company (HINALCO) |